Status: | runing |
Registration Date: | 92-91 |
master
Kerman Province Gas Co.
Social status
Kerman
contract type
PC
main contractor
sayal gostar company
description
6 and 10-inch gas pipeline Haji Abad - Arzuiyeh of Tupac receiving station Haji Abad existing gas pipeline begins and In a way station between the milk and Vakil Abad in the km 44, 389 + 24 main line sizes 6 inch split and until the Vakil Abad valve station 06 + 949 km in length continues Finally, 10-inch gas pipeline Arzuiyeh receiving station in km 51+ 290.15 Tupac Arzuiyeh ends.