status: | Completed |
Registration Date: | 87-86 |
master
Esfahan Province Gas CoSocial status
Esfahancontract type
PCmain contractor
sayal gostar companydescription
16-inch diameter steel pipe laying operations of the transmission line and power line steel tubing pressure of 250 PSI operations with the installation of all fittings, flanges, valves and related facilities and installing ponds Lions, Receiving Stations Tupac installation, construction and installation Aytgah CGS capacity of 100 thousand cubic meters per hour, construction of a cathodic protection station in Kashan